Türkiye’s Ministry of Energy and Natural Resources (ETKB) has approved the land subdivision (parcellation) plan for the Lityum EDT 1 solar power plant (GES) project, covering parcels 5 and 6 of block 122 in the Şıhahmetli neighbourhood of Polatlı district in Ankara province. According to the ministry’s announcement of 27 November 2026, the plan was put on public display on the same day for 15 days.
Approved by ministerial decision of 25 November
According to the announcement, the plan was approved by the ministry’s Ministerial Approval No. 438890 of 25 November 2026, under the Regulation on Zoning and Permit Procedures for Electricity Generation Facilities Based on Wind and Solar Energy, published in Official Gazette No. 33319 of 24 July 2026.
15-day display period
Under Article 18 of Zoning Law No. 3194 and Article 9 of the same Regulation, the plan is displayed for 15 days from 27 November 2026 on the ministry’s web page for plans on display and on the notice board on the ground floor of its main service building. The announcement does not state the plant’s installed capacity, its developer or what “EDT” in the project name stands for.
Sources
- Republic of Türkiye Ministry of Energy and Natural Resources, Lityum EDT 1 GES land subdivision plan announcement, 27.11.2026: enerji.gov.tr/duyuru-detay?id=30681
- ETKB, Zoning and Subdivision Plans on Display: enerji.gov.tr
Image: Republic of Türkiye Ministry of Energy and Natural Resources