Contents
Best bids have been set for 11 lots across 9 provinces in Türkiye’s YEKA GES-2026 solar auctions. According to the results table dated 3 November 2026, contribution fee bids for the total of 785 MWe of capacity add up to EUR 31,585,000.
Highest contribution fee bid in Konya
By lot, the highest total contribution fee bid was submitted for the 110 MWe G26-Konya GES by İş Enerji Yatırımları A.Ş.: EUR 64,000 per MW, or EUR 7,040,000 in total. It was followed by the 85 MWe G26-Kahramanmaraş-2 GES (EUR 5,100,000), the 55 MWe G26-Malatya-1 GES (EUR 5,005,000) and the 50 MWe G26-Kahramanmaraş-3 GES (EUR 3,700,000).
The highest per-MW bid was EUR 91,000, submitted by Ezel Mensucat San. ve Tic. A.Ş. for G26-Malatya-1 GES. The lowest per-MW bid shown was EUR 12,000, from İklim İnvest Enerji ve Teknoloji Yatırımları A.Ş. for G26-Ankara-2 GES.
EGESA and Temmuz Güneş-named companies each hold three lots
According to the table, EGESA Elektrik İnşaat Enerji Üretim A.Ş. submitted the best bid in the Diyarbakır (200 MWe), Mardin-2 (120 MWe) and Batman (25 MWe) lots, together 345 MWe and EUR 6,260,000 in contribution fee bids. Companies named Temmuz Güneş Denizli Enerji Üretim and Temmuz Güneş Kahramanmaraş Enerji Üretim appear as best bidders in the Denizli (30 MWe), Kahramanmaraş-2 (85 MWe) and Kahramanmaraş-3 (50 MWe) lots, together 165 MWe and EUR 10,600,000.
Purchase price bids
The purchase price bid is listed as 3.25 euro cents/kWh in 10 of the 11 lots. Only the 25 MWe G26-Batman GES shows 3.21 euro cents/kWh. In the sealed financial bid column, Konya shows 3.28, Malatya-1 3.84, Diyarbakır 3.85 and Batman 3.85 euro cents/kWh; the other lots show 3.25.
Results lot by lot
| Auction | Capacity (MWe) | Applicant | Sealed financial bid (euro cents/kWh) | Purchase price bid (euro cents/kWh) | Contribution fee (EUR/MW) | Contribution fee (EUR) |
|---|---|---|---|---|---|---|
| G26-Denizli GES | 30 | Temmuz Güneş Denizli Enerji Üretim San. ve Tic. A.Ş. | 3.25 | 3.25 | 60,000 | 1,800,000 |
| G26-Ankara-1 GES | 40 | Erser Grup Tarım Ürünleri San. ve Tic. A.Ş. | 3.25 | 3.25 | 22,000 | 880,000 |
| G26-Ankara-2 GES | 30 | İklim İnvest Enerji ve Teknoloji Yatırımları A.Ş. | 3.25 | 3.25 | 12,000 | 360,000 |
| G26-Konya GES | 110 | İş Enerji Yatırımları A.Ş. | 3.28 | 3.25 | 64,000 | 7,040,000 |
| G26-Kahramanmaraş-2 GES | 85 | Temmuz Güneş Kahramanmaraş Enerji Üretim San. ve Tic. A.Ş. | 3.25 | 3.25 | 60,000 | 5,100,000 |
| G26-Kahramanmaraş-3 GES | 50 | Temmuz Güneş Kahramanmaraş Enerji Üretim San. ve Tic. A.Ş. | 3.25 | 3.25 | 74,000 | 3,700,000 |
| G26-Malatya-1 GES | 55 | Ezel Mensucat San. ve Tic. A.Ş. | 3.84 | 3.25 | 91,000 | 5,005,000 |
| G26-Diyarbakır GES | 200 | EGESA Elektrik İnşaat Enerji Üretim A.Ş. | 3.85 | 3.25 | 16,000 | 3,200,000 |
| G26-Mardin-2 GES | 120 | EGESA Elektrik İnşaat Enerji Üretim A.Ş. | 3.25 | 3.25 | 18,000 | 2,160,000 |
| G26-Batman GES | 25 | EGESA Elektrik İnşaat Enerji Üretim A.Ş. | 3.85 | 3.21 | 36,000 | 900,000 |
| G26-Elazığ GES | 40 | Ecogreen Elektrik Enerji Üretim A.Ş. | 3.25 | 3.25 | 36,000 | 1,440,000 |
| Total | 785 | 31,585,000 |
The data above is based on the YEKA GES-2026 auction results table dated 3 November 2026. The table does not include information on contracts or capacity allocation procedures.
Sources
- YEKA GES-2026 auction results table, 3 November 2026 (Google Sheets)
Image: Ministry of Energy and Natural Resources